Thank you to everyone who joined us for the Ribbon Cutting and Open House to celebrate our new facilities at Muskego High School. We are deeply grateful for the unwavering support of our families and community. These new spaces will provide endless opportunities for our current and future students to learn, grow, and thrive both inside and outside the classroom. We can’t wait to see what the future holds!
Autos Lab
Art Lab
Engineering & Design
Culinary Arts
Health Science
Practice Facility
Fitness Facility
Renovated Gymnasium
STEAM Wing
Summer 2024 Update
Please join us on Wednesday, August 28 from 5:30 p.m. to 8:00 p.m. for a Ribbon Cutting and Open House to celebrate the new facilities at Muskego High School.
Spring 2024 Update
May 2024 - Construction of the Lakeview Elementary gymnasium is complete, and PhyEd classes are being held in the gym. We celebrated with a special ribbon cutting assembly with the whole school, district administrators, representatives from CG Schmidt, and the MHS drumline. Thank you to our staff, students, families, and community for their support and enthusiasm for this beautiful facility that will serve many in our community for years to come.
Winter 2023-24 Update
Lakeview Elementary
Construction progress of the Lakeview Elementary gymnasium remains on schedule. Installation of the gym floor is scheduled for February 2024. If construction progress remains steady, we will have occupancy by the end of the school year.
Lakeview Gymnasium
Muskego High School
S.T.E.A.M. Addition - The S.T.E.A.M addition is nearly enclosed. Below are photos taken at the beginning of January 2024.
Autos Shop
S.T.E.A.M. Corridor
S.T.E.A.M. Aerial View
Health Science + Practice Facility Addition - The expanded parking lot was finished over the summer for the beginning of the 2023-24 school year. The new practice facility is enclosed, and turf will start being installed in February 2024.
Health Science Aerial View
Fitness Facility
MHS Music Department Tour
Summer 2023 Update
Lakeview Elementary
Sitework began in July 2023. Below is an aerial view of the progress of the gym addition.
Muskego High School
Health Science + Practice Facility Addition - Below is an aerial view of the south construction at MHS. The expanded parking lot will include 171 stalls. The new practice facility is taking shape.
S.T.E.A.M Addition - Sitework is underway for the S.T.E.A.M. addition on the north end of MHS. Below is an aerial of the mid-summer construction progress.
Groundbreaking Ceremonies
Please join us in celebrating the start of construction for the new facilities at Muskego High School and Lakeview Elementary.
Lakeview Elementary
Tuesday, June 6 at 11am-11:30am
Guest arrival: 10:45am
Location: Lakeview Elementary - 26335 Fries Ln, Wind Lake, WI 53185
Parking: Parking is available at the rear of the building. Please enter at the east driveway. Additional street parking available on W Wind Lake Rd.
See below map. Parking in blue. Ceremony location in green.
Muskego High School
Thursday, June 15 at 11am-11:30am
Guest arrival: 10:45am
Location: Northwest end of Muskego High School - W185S8750 Racine Ave, Muskego, WI 53150
Parking: Parking is available on the northwest side of the building off of Woods Road
See below map. Parking in blue. Ceremony location in green.
Tour: Optional tour of Muskego High School will be offered after the ceremony
Project Timeline
A phasing plan has been prepared to reflect a timeline for sections of construction at Muskego High School and Lakeview Elementary.
November 2022 Update
The Master Planning Committee is wrapping up the final design before bidding the expansion and renovation projects at Muskego High School and Lakeview Elementary. In the coming months, we expect to see the arrival of construction trailers and the start of earthwork at key locations.
We are planning for a fall of 2024 completion date for the projects that were approved during the 2022 Referendum.
October 2022 Update
October 4, 2022 - The Plan Commission approved the Building Site Operation Plan for the MHS expansion.
Below is a video walkthrough of the MHS Design Development.
Draft Renderings
Following a successful facilities referendum in April, District teams continued to meet during the summer to design the MHS S.T.E.A.M. and Health Science additions, as well as the new gymnasium at Lakeview. Below are some draft renderings of spaces, pending Plan Commission approval. The projects will be bid out this fall/winter and will begin construction in the spring. Thanks to all who took time this summer to lead and attend user group meetings!
Below are draft renderings of the spaces.
Lakeview Gymnasium Addition
MHS S.T.E.A.M.
Northwest addition at Muskego High School (Engineering, Manufacturing, Automotives, Art, Construction, Welding, Robotics, Project Lead The Way, Culinary Arts)
Autos Lab
Culinary Arts
North Gym Renovation
North Gymnasium, Dance, and Wrestling spaces
Health Science Addition
South addition at Muskego High School (Classroom, Locker Rooms, Fitness Center, Athletic Training, Indoor Practice Facility)
Band and Choir Renovations
Renovation to expand existing music department is included in the project but not referendum dollar amount, as it will be funded through the operating budget.
Relocation of Grounds-Maintenance Garage from MHS to ESC
The current grounds shop is located in the middle of the S.T.E.A.M. addition. Relocating the shop is necessary for construction and also will provide a location for grounds workers that is central to the athletic complex.
On April 5, 2022, both referendum questions passed.
On January 20, 2022, after many planning discussions, the school board approved two questions to be placed on the April 5th ballot.
Question 1
Shall the Muskego-Norway School District, Waukesha and Racine Counties, Wisconsin be authorized to issue pursuant to Chapter 67 of the Wisconsin Statutes, general obligation bonds in an amount not to exceed $27,800,000 for the public purpose of paying the cost of a school facility improvement project consisting of: construction of an addition for technical education, science, technology, engineering and math areas, and renovations at the High School; construction of an addition and renovations for a gymnasium and conversion of the current gymnasium into a cafeteria at Lakeview Elementary School; site improvements; and acquisition of related furnishings, fixtures and equipment?
Question 2
Shall the Muskego-Norway School District, Waukesha and Racine Counties, Wisconsin be authorized to issue pursuant to Chapter 67 of the Wisconsin Statutes, general obligation bonds in an amount not to exceed $16,800,000 for the public purpose of paying the cost of a school facility improvement project consisting of: construction of additions for medicine and health sciences areas and an indoor practice facility, and renovations at the High School; site improvements; and acquisition of related furnishings, fixtures and equipment?
Residents of the district were mailed a paper survey which included a unique survey access code to participate online. More than 3,055 responses were collected (52% parents and 48% non-parents).
Survey Results
S.T.E.A.M
Health Science
Practice Facility & Band
Lakeview Gym
Budget
$24,400,000
$9,100,000
$9,500,000
$3,400,000
All Residents
74%
71%
56%
70%
Parent
82%
77%
65%
74%
Non-parent
63%
61%
44%
64%
Below are projects that were included in the October 2021 Community Survey
Project 1
Update/Expand the tech ed (shop) and STEAM areas
There is a growing demand for employees in the engineering, construction, and manufacturing fields. However, our current classrooms and labs, which were originally built in the 1960s, are too small and limit our ability to expand course offerings in woods/construction/building trades, metals, robotics, fabrication, Project Lead the Way (PLTW), and auto repair. This project would also update and expand hands-on learning opportunities for students studying science, technology, engineering, art, and math (STEAM).
Project 2
Update/Expand medicine/health sciences areas
The high school’s academic and career planning efforts revealed that nearly 25 percent of our student body is interested in pursuing a career in health sciences. The proposed addition would provide both classroom and experiential/hands-on learning spaces for students interested in careers such as physical therapy, nursing, athletic training, and other health sciences. This space. would allow us to expand the partnerships developed with our Connect Academy, which brings in healthcare professionals to support the daily learning of our students.
Project 3
Expand band & choir and build an indoor performance lab
Enrollment in our band and choir programs has grown significantly since these classrooms were constructed in 2003. Both areas are unable to support full operations and have outgrown storage capacity. The proposed renovation will provide needed space for today as well as future growth. The project would also include a performance lab, providing indoor space for physical education, youth groups, athletics, marching band practice, and dance, all of which are seasonally impacted by limited indoor space and seasonally poor weather. Opportunities would be available for the community to use for fitness and indoor walking.
Project 4
Build a gym and create a dedicated cafeteria at Lakeview Elementary
Lakeview Elementary is the only school in our district without a dedicated cafeteria. Consequently, lunch is served in the gym, requiring staff to set up and take down tables daily. This situation reduces the time students have to eat lunch and creates scheduling challenges for class offerings, physical education, performances, and after-school programming. The current gym is not regulation size, and therefore cannot be used for competition. The project would build a single-court gym and convert the existing gym to a dedicated cafeteria.